Project management, operation, maintenance and repair of all facilities,equipment and general services of water treatment plant of BandarAbbas

 The nominal capacity of this refinery is 1 m3 / s which is practically used up to a capacity of 0.9 m3 per second

* The second phase of the treatment plant with a nominal capacity of 2 cubic meters per second and, in special circumstances, is up to

2.4cubic meters per second

* Located 7 km away from Bandar Abbas-Minab road east of Bandar Abbas

Ownership of land with an area of about 11.5 hectares and a size of 250 * 460 meters